Task Details

Navigation:  Reference > Dialogs >

Task Details

Previous pageReturn to chapter overviewNext page

From the Tasks menu in Tasks, select New or Edit

The Task Details dialog enables you to modify details of a task.

Descriptions

Description: Specifies a short description of the task.

Priority: Sets the tasks's priority.

Type: Specifies type of the task.

Category: Sets a category used to organize tasks.

Start Date: Specifies a date when the task starts.

Due: Specifies a date when the task is due.

Plot on Gantt Chart: Specifies whether to plot the task on the Gantt chart.

Completion: Specifies completion percent of the task

Completed: Sets the date and time when the task was completed.

Save at root level: Specifies whether to create at the current hierarchy level or as a root-level task.

See also


Tasks